Office Of Rail And Road: Independent Inquiry Into (Some Of) The Timetable Disruption In May 2018

We hesitate to mention this, as it’s a report into the timetable debacle which somehow manages to avoid any analysis of TPEs part in it, and doesn’t manage to mention the impact on our stations until the end of the last appendix.

We find it difficult to take seriously a report which ignores the train company whose performance has been consistently as poor as Northern’s.

The conclusion of the report appears to be a bit like Murder On The Orient Express. They all did it. Except the ones who weren’t there.

Links to the report and the Yorkshire Post article below. Nothing interesting to say about our abysmal train service, in fact nothing at all to say about our abysmal train service.

http://orr.gov.uk/rail/consumers/inquiry-into-may-2018-network-disruption

https://www.yorkshirepost.co.uk/news/chris-grayling-s-department-criticised-in-damning-timetabling-chaos-inquiry-1-9357640

Posted in timetable changes | Tagged | Leave a comment

“Transport for the North Board takes decisive action on the future of the North’s railways”

We don’t want “the same frequency of local trains” at the end of 5 years of disruption. We want two trains per hour throughout the day. That’s the same as anywhere else in the Manchester and Leeds travel to work areas, not the same inadequate service as we have now.

[Transport for the North press release, Thursday 13th September 2018]

The Transport for the North Board met in Sheffield today and welcomed the allocation of nearly £3bn over the next five years by government as the first phase of upgrading the Transpennine railway line.

But the Board also made a clear call to ensure that designs for the Transpennine Route Upgrade programme should allow for the full delivery of all outcomes originally agreed:

• Target journey times of 40 minutes between Leeds and Manchester and 62 minutes between Manchester and York
• 6 long distance trains per hour, whilst allowing for the same frequency of local trains
• Greater capacity through provision for longer trains
• The highest reliability levels of any long-distance service in Britain
• Provision for freight, with the option to transport containers by rail (which is not currently possible)

Furthermore, Transport for the North wants to ensure that any upgrades are environmentally sustainable and do not have a negative impact on air quality.

The Board emphasised the vital importance of minimising disruption whilst major upgrade works are completed.

Transport for the North Chairman John Cridland said,

“Our call to government is an example of the North clearly stating its intent and ambition with a single voice through Transport for the North. We are pleased that the Government is showing continued commitment to the Transpennine Route Upgrade, which is a vital component of the Northern Powerhouse, and we look forward to working closely with the Department for Transport and Network Rail as detailed design begins.”

On the subject of rail performance, Northern, TransPennine Express and Network Rail gave a presentation on their improvement plans and our Board expressed frustration around performance in general and in particular the industry’s short term plans to improve the resilience of the network.

Whilst recognising that performance has improved and stabilised since the major disruptions following the May timetable change, board members repeatedly challenged representatives from Northern, Trans Pennine Express and Network Rail about the reasons for continued delays, cancellations and short-formed trains.

Also at the meeting, it was announced by Transport Minister Jo Johnson that in response to our letter of 2 August to Chris Grayling calling for a single person to oversee both infrastructure and train operations, Richard George has been appointed, working closely alongside Transport for the North.

With extensive rail industry experience, Mr George has served as Chairman on the boards of First Group, First Great Western, First Great Eastern and First North Western. He was Director of Transport at the London Olympics and is currently Global Head of Rail Infrastructure at SNC Lavelin.

He will assume his role following final agreement between Transport for the North and the Department for Transport on the details of the appointment.

Transport for the North is also pleased to announce that terms have been agreed between the Rail North Partnership and Northern on compensation for some regular travellers in the most disrupted areas. An announcement will follow from the train operating companies with the scheme implemented as soon as possible.

The news on compensation follows the announcement yesterday of an enhanced Delay Repay scheme for Northern passengers. From December, passengers whose journeys are disrupted by 15-29 minutes will also be able to claim compensation under the Northern Delay Repay scheme – currently only those delayed by 30 minutes or more can claim.

John Cridland, Chairman of Transport for the North, said:

“Our focus as a Board is on a rail service that is reliable, resilient and environmentally sustainable and we will continue to press the industry in order to deliver on our vision.

“Richard George’s appointment is a major step forward for the travelling public of the North and a clear indication that Government is listening to the views of Transport for the North. It will enable us to address the structural issues relating to the rail industry that have had a major impact on passengers, while the imminent implementation of the further compensation scheme we have been seeking will help passengers who were disrupted earlier this year.”

Transport for the North Board takes decisive action on the future of the North’s railways

Posted in TfN, Transpennine Route Upgrade | Tagged , | Leave a comment

Trans-Pennine rail £2.9bn upgrade will cause five years of route closures, longer journeys and less capacity

A letter from Network Rail to the Transport Secretary sets out some of the potential outcomes of the proposed Transpennine Route Upgrade (TRU), and the potential disruption during a construction period of five years.

 “Communities at Ravensthorpe, Mirfield, Batley, Dewsbury, Marsden and Slaithwaite would be hugely affected as many rail services would need to become bus replacements”.

“This is attempt to test public and political reaction”.

“I am disappointed that there was not a formal briefing for MPs in whose constituencies construction work will take place.

“The same tactic of drip feeding bad news has already been used to lower expectations regarding the full electrification of the line, which was initially promised by the Conservative government.

“My initial concern is that the inevitably extensive construction work in the Colne Valley will hit our services and disrupt the wider community.

“It is my hope, however, that we will see every effort being made to schedule work so that this stretch is closed for the minimum period of time whilst trains by-pass our stations.

“Potentially, the upgrade is positive, if it delivers a modern railway providing improved capacity, frequency and reliability.

“This must deliver these benefits for passengers from Huddersfield, Slaithwaite and Marsden, rather than being exclusively focused on passengers travelling between Manchester and Leeds.”

[Thelma Walker, Colne Valley MP]

“In the long term this will bring real benefits but in the short term it could cause a lot of grief because of the scale of building work taking place.

“We would hope they would do some proper consultation with local politicians, and more importantly with the wider community, before anything is decided.

“What I worry about is because we are on the fringes of Leeds and Manchester, when decisions are made the emphasis is on the passengers from the big cities and not enough consideration is given to us.

“It’s clear from the May timetable scandal that people from Slaithwaite and Marsden have probably suffered more than anybody else.

“We’ve already been let down in terms of what was promised.

“I’ve seen people in tears on the platforms when their trains don’t turn up.

“We’ve heard of people getting their wages docked £20 every time they’re late.

“It’s vital we get more people on trains and less in cars, but at the moment it’s going the other way.”

[Cllr Rob Walker, Chair of SMART]

[Article from the Yorkshire Post, Thursday 13 September 2018, follows]

 Trans-Pennine rail £2.9bn upgrade will cause five years of route closures, longer journeys and less capacity

The £2.9bn upgrade of trans-Pennine rail repeatedly promoted by Chris Grayling will cause “significant disruption” for five years, including route closures for up to 39 weeks a year, longer journey times and less seats on trains, a senior transport official has said.

A letter from Rob McIntosh, a route managing director at Network Rail, to the Transport Secretary, describes the disruption that could be caused if the project is to be completed by 2024.

The document, which has emerged online, also says attempting to make further improvements “would add additional risk to the programme”, although it is understood that parts of the line will be electrified, but not the entire route.

Mr Grayling has repeatedly highlighted the Government’s £2.9bn investment in upgrades to the Victorian railway, which has long been blighted by delays and a lack of capacity, peaking this summer during the timetabling chaos.


Mr McIntosh said the work would eventually “transform” passengers’ experience between York, Leeds and Manchester through “significantly” reduced journey times, more capacity on trains, and upgrades to stations along the route.

But he warned it “cannot be delivered without significant disruption” due to having to upgrade an old railway in the “inherently challenging” landscape of the Pennines.

Network Rail will carry out the works to minimise disruption around key seasonal economies such as tourism, university terms and Christmas markets, “but delivering this level of investment to ensure value is maximised cannot be done without disruption”.

Trains will be diverted through other routes such as through the Calder Valley, but

“in practice to achieve the improvements we are seeking we will need to close some part of this (trans-Pennine) route for up to 39 weeks per year between 2020 and 2024,”

Mr McIntosh said.

“This will see journey times increase by 15 to 25 minutes and also constrain capacity over the period.”

Commenting on the letter, Mr McIntosh told The Yorkshire Post:

“The message for me is that delivering £3bn of investment on one of the most contested parts of the network is going to be disruptive to local communities, economies and passengers.

“What we have put forward we think delivers the best benefits and outcomes for passengers in the shortest time scales while maintaining the connectivity of the community. “

Conservative MP for Thirsk and Malton Kevin Hollinrake said disruption was unfortunately inevitable with works “of that magnitude” while suggesting Ministers could ask Network Rail to potentially shorten the timescale.

The revelations also highlight the lack of other routes across the Pennines and the need to get on with building Northern Powerhouse Rail across the region by 2032, he said.

Mr Hollinrake added:

“The Treasury and the Department for Transport (DfT) seem very supportive (of that idea), they are waiting for this business case from Transport for the North which we think will be with us by the end of the year, but I’m still hoping for a Budget commitment for that nevertheless to say ‘all being well with the business case we’re going to support it’.”

The Department for Transport said the improvements were being phased over five years to “keep disruption to a minimum”.

A spokeswoman said:

“We are investing £13bn in transport in the north, and are planning to invest £3 billion upgrading the trans-Pennine route – one third of our budget for rail upgrades between 2019-24. This is our biggest planned investment project in the next five years, and will reduce journey times, increase capacity and improve stations.

“We are working closely with Network Rail and Transport for the North to deliver these vital improvements that passengers want and deserve as quickly as possible. However, we also want to keep disruption to a minimum, which is why the upgrade will be delivered in phases from Spring 2019.”

https://www.yorkshirepost.co.uk/news/transport/trans-pennine-rail-2-9bn-upgrade-will-cause-five-years-of-route-closures-longer-journeys-and-less-capacity-1-9347535

Posted in Electrification, Marsden, Northern Hub, Slaithwaite, Transpennine Route Upgrade | Tagged , , , , | Leave a comment

Amendments to TransPennine Express timetable from December 2018

Received the following from TPE today.

Whilst the loss of regular through trains to Leeds is disappointing, as it was one of the few benefits of the May 2018 timetable, it has to be recognised that the experience of the past four months, as evidenced by over 600 cancellations in just 16 weeks, has shown that it wasn’t possible to operate the May 2018 timetable reliably.

SMART would like to see a direct service to Leeds restored when practicable, but not at the expense of reliability. At the moment, there’s a trade-off between the two.

Hopefully this will see an end to the farce of trains being turned round at Stalybridge on a regular basis.

 

Amendments to TransPennine Express timetable from December 2018

 

As you will be aware, our services have been affected by a range of performance issues since the introduction of the May 2018 timetable which has affected the punctuality and reliability of our services on the North TransPennine route.

 

We wanted to take the opportunity to outline performance improvement changes we will be introducing to the timetable in December to provide greater resilience for services on this route.  Since May, over 70% of delays to our services have been caused by factors outside the direct control of TransPennine Express.  We have therefore worked with Network Rail and Northern to develop an industry plan to deliver improvements to train service performance.

 

With the agreement of Transport for the North and the Rail North Partnership, and following consultation with their local authority members, as part of the timetable change on 09 December 2018 we will make amendments to a small number of TransPennine Express services as follows:

 

  • The current service that operates in each direction between Manchester Piccadilly and Leeds, calling at Stalybridge, Greenfield, Marsden, Huddersfield, Deighton, Mirfield, Ravensthorpe, Dewsbury, Batley and Morley will from this date be operated by two separate trains as follows:

    • Manchester Piccadilly to Huddersfield, calling at Stalybridge, Greenfield, Marsden and Slaithwaite

    • Huddersfield to Leeds calling at Deighton, Mirfield, Ravensthorpe, Dewsbury, Batley, Morley and Cottingley

  • The current service that operates between Hull and Manchester Piccadilly will have two stops removed and will no longer call at Batley or Slaithwaite.  These calls will now be made in the newly introduced Huddersfield to Leeds and Manchester to Huddersfield services respectively (as above)

  • We will make changes to increase the turnaround time of Newcastle/Middlesbrough to Manchester Airport services at Manchester Airport.  This does not alter the timetable for customers but will improve the reliability of these services

 

We are confident these changes will provide customers with a more resilient and reliable service.

 

These changes have also enabled us to make progress on responding to stakeholder requests for improved local station connectivity between Manchester and Huddersfield and Leeds and Huddersfield and to reduce the number of stations calls between Hull and Manchester.

There are no other structural changes being made to the timetable at December.  Timetables (on-line, printed and published at stations) will be available in advance of the winter timetable change as per normal.  We will circulate links to these timetables once available.

We will continue to closely monitor performance and assess the impact and effectiveness of these changes and consider, particularly in light of the performance of services in and around Manchester, whether further amendments will be required to improve train service performance.

We would also like to apologise again to all customers who have been affected by any delays or cancellations since the May 2018 timetable was introduced.  Compensation for eligible season tickets holders is available (https://compensation.tpexpress.co.uk/) and compensation is provided from any delays of 30 minutes or more via our Delay Repay scheme (https://www.tpexpress.co.uk/help/delay-repay-compensation).  Claims should be made by 01 October 2018 for the May 2018 compensation scheme.

We look forward to introducing these service changes on 09 December 2018.

Provisional timings have now been published in the National Rail journey planner, and show most trains at Slaithwaite on the opposite half hour from now, plus some changed timings on Northern’s peak extra trains that call at Marsden in the westbound direction. These will now run from Huddersfield to Marsden, wait in platform 3 for 25 minutes, and then continue to Manchester.

It appears there is one through train to Leeds from Marsden (0610) & Slaithwaite (0613), and two through trains from Hull/Leeds which continue to call at Slaithwaite (Leeds 1640, Slaithwaite 1707 & Leeds 1740, Slaithwaite 1807).

Posted in Marsden, Slaithwaite, timetable changes, Transpennine Express | Tagged , , , | 1 Comment