Category Archives: Transpennine Route Upgrade

Weekend timetable changes, 4 & 5 October & weekday timetable changes 6 to 24 October

We know that we have only just come to the end of a month of bus replacement, but Huddersfield station and the route between Stalybridge and Deighton will be closed again next weekend (4/5 October) with bus replacement. Then on … Continue reading

Posted in Marsden, Slaithwaite, timetable changes, Transpennine Express, Transpennine Route Upgrade, weekend rail services | Tagged , , , , , | Leave a comment

Huddersfield Station Closure and Rebuilding

The month long closure has come to an end, and Huddersfield station now has two through platforms plus the bay platform for the Penistone Line. The platforms have been renumbered, so the Penistone line platform is platform 1, the former … Continue reading

Posted in Huddersfield Railway Station, Marsden, Slaithwaite, timetable changes, Transpennine Express, Transpennine Route Upgrade | Tagged , , , , , | Leave a comment

The End Of A Month Of Bus Replacement

We are now at the end of four weeks of bus replacement during the Huddersfield station closure. It has been mostly reliable, but with just enough occasions when buses have gone off route, departed early or not turned up at … Continue reading

Posted in Huddersfield Railway Station, Marsden, Slaithwaite, Transpennine Express, Transpennine Route Upgrade | Tagged , , , | Leave a comment

Slaithwaite and Marsden Action on Rail Transport Update – September 2025 

We’re one week into the line closure – three weeks to go! Closures: Further detail can be on the SMART or TPE websites. All being well, things should be back to normal from Monday 29th September – though direct trains from Slaithwaite and Marsden to … Continue reading

Posted in Campaigning, Marsden, METRO/WYCA, Slaithwaite, Transpennine Express, Transpennine Route Upgrade, weekend rail services | Tagged , , , , , | Leave a comment