Accessibility Update – Marsden Station

Accessibility at Marsden station has been raised with the Secretary of State both by Thelma Walker MP and by Cllr Donna Bellamy.

Until May 2018, most westbound trains used platform 3, with level access. From 20th May 2018, most eastbound trains used platform 2, accessed by steep steps and with a height difference of 51cm between the train and the platform. [SMART had advised against this, but we were ignored.] The reasoning behind the change is that use of platform 2 saves 1 ½ to 2 minutes, which makes a difference on a line as busy as Huddersfield-Stalybridge.

The kindest thing to say is that the train companies and Network Rail didn’t realise that the height gap was a great as it was.

It’s evident that use of platform 2 has been troublesome operationally. First of all TPE changed their operating practice to only open one centre door at Marsden westbound, then in January 2019 TPE stopped using platform 2 on a regular basis. It’s this latest change which has meant that all westbound trains run two minutes late (or should that be two minutes later than they would otherwise have been).

Thelma Walker MP now reports:

I am delighted that after raising the issue of accessibility at Marsden Station with the Secretary of State for Transport in the Chamber and in private meetings, action is being taken to improve platform access.

As a temporary measure, an Easy Access Area will be put in place on Platform 2, and there is a longer-term plan to raise the whole length of the platform as part of the Transpennine Route Upgrade.



Cllr Donna Bellamy adds:

Marsden station platform 2, just had further update after an assessment has taken place the Original solution was Harrington Humps for 1x set of doors on P2 at Marsden. The Plan has since changed to be a ‘Dura’ platform raise for the full (99m) length of the platform. this does mean that the work completion will be slightly longer but should be done by the end of March.

Of course, there needs to be a bit of perspective here. This is a mitigation of a problem which should never have been created in the first place. It is no substitute for full disabled access to all platforms.

When we met the Secretary of State we asked for confirmation that the Transpennine Route Upgrade (TRU) would provide full disabled access to all platforms at Mossley, Greenfield, Marsden & Slaithwaite. We do not yet have an answer.

Posted in Marsden, Transpennine Route Upgrade, Uncategorized | Leave a comment

Discussions about the December 2019 timetable

The following is taken from West Yorkshire Combined Authority Transport Committee’s agenda papers for 11th January, and specifically from WYCA’s formal consultation response on the proposed December 2019 timetable.

2. Local services between Leeds and Manchester

As you will be aware, the service patterns on the core Diggle axis have been the focus of much attention both before and after the May 2018 timetable change, both with regard to the connectivity and service levels timetabled and to real-world operating performance. The Combined Authority’s consistent position has been not to favour “skip-stopping” or similar patterns on the rail network, and in this respect the Combined Authority welcomes the December 2018 changes as representing the beginning of a move away from this, albeit only the beginning.

Clearly, this route is highly capacity-constrained and some improvements will need to await the Trans-Pennine Route Upgrade programme (TRU), but we believe that some enhancements both can and should be delivered in the shorter term. These include:

The restoration of a “true” stopping service between Manchester and Huddersfield, operating at least once per hour and calling at all stations.

An increase in service levels at Slaithwaite and Marsden to 2tph in the AM and PM peaks (in each case in both directions), again to restore pre-May-2018service levels to those stations. It is accepted that under some service combinations it might not be possible for all the additional peak-only trains to stop at all stations, and a pragmatic view will be needed as to which “extra” trains can accommodate stops at these stations, provided that at least 1tph does stop at all stations between Huddersfield and Stalybridge.

The Combined Authority notes that the current services at Slaithwaite and Marsden, taking TPE and Northern services together, fall short of franchise requirements in the peaks, as well as being inferior to the position before May 2018. While the noncompliances may directly relate to Northern’s rather than TPE’s Train Service Requirement, the reality of this corridor is that the two operations are inextricably linked, and the constraints “caused” by one operator’s service often cause issues for the other. In any event, we retain an open mind as to the potential merits of any “remapping” of certain services if this provides a route to unlocking the service levels we wish to see.

In the longer term, Combined Authority policy favours 2tph on the stopping service between Huddersfield and Leeds via Dewsbury (with the Manchester – Calder Valley – Brighouse – Dewsbury – Leeds service becoming semi-fast), but accepts that this is unlikely to be feasible without additional infrastructure, for which we look to TRU.

3. Operational Performance (Punctuality and Reliability)

Performance on the North Trans-Pennine route continues to fall far below reasonable expectations and franchise standards. Indeed, by some measures Slaithwaite station has the least reliable services anywhere in Britain, and six out of the top ten least reliably-served stations are on this line; amongst the top 100 busiest stations in the country, nine of the ten with the least reliable services are on the TPE network, including Huddersfield as the least reliable large station of all, with Leeds and York also featuring.

Day-to-day operating decisions have exacerbated the impact of the poor performance: we have received numerous reports of trains that should travel to Manchester Airport being terminated at Manchester Victoria, from where the onward journey to the Airport is anything but straightforward; of stops at Slaithwaite or Marsden being omitted; and of Scarborough trains only reaching Malton – amongst other examples. Where trains only run hourly, the impacts on travellers’ journeys is often unacceptable, and we have heard of situations where such steps have been taken to consecutive trains. This is harming both rail travel and the economies of the communities that depend on rail connectivity. So not only the structure of the timetable but also the management of performance on a day-to-day basis needs closer and improved management focus.

The Combined Authority is aware that TPE is taking steps to seek to mitigate this, including the timetable changes being introduced in December 2018, and it has been pleasing to see evidence of TPE moving away from a “blame culture” towards working positively to tackle the root-causes of the problems. The Combined Authority is in principle supportive of any timetable interventions designed to improve performance, provided that they do not entail compromises to connectivity (either of TPE’s own services or consequent impacts on other operators’ services) that go beyond acceptable limits, as for example removing station-stops or curtailing local services would be likely to.

In this spirit, the Combined Authority has not opposed the principle of the breaking of the cross-Huddersfield links on local services that have proved incapable of being maintained reliably. Similarly, we would not necessarily oppose re-examining the clockface structure of fast services between York/Leeds and Manchester if, for example, a move away from current structure could greatly increase performance or unlock local connectivity at intermediate stations.

Posted in METRO/WYCA, Transpennine Express, Uncategorized | Leave a comment

Trans-Pennine Upgrade Update, 25/09/2019

It’s difficult to identify quite what is meant by the Transpennine Route Upgrade.

First there was the Manchester Hub, which then became the Northern Hub, which was “approved in full” several years ago. This was a bit misleading, as it originally included reopening both the disused Standedge tunnels to give four tracks between Marsden and Diggle, but this was then replaced by electrification, so what was approved “in full” was less than what was originally proposed.

All of which goes to show that government announcements often aren’t worth the paper they are written on. Possibly not a huge surprise there.

The Northern Hub was supposed to be completed by 2018, but the only part of it to have been completed is the Ordsall Curve in Manchester. It was the reorganisation of train services to utilise the Ordsall curve which resulted in the May 2018 timetable meltdown which affected Slaithwaite, Marsden, Greenfield and Mossley worse than anywhere else.

Some of the definite commitments in the Northern Hub have been quietly abandoned or deferred indefinitely. In particular, electrification from Manchester to Stalybridge, and on to Huddersfield, Leeds and York/Selby has not been started and it’s unclear when or indeed whether most of it will happen.

The current proposal, we think, is the Transpennine Route Upgrade. There’s very little that’s known with certainty about TRU. The budget, allegedly, is £2.9 billion (which, incidentally, is less than the cost overrun on London Crossrail). Anyone we talk to in the railway industry either denies knowledge of what it will involve, or says they are sworn to secrecy (it’s not stated who is swearing them to secrecy), or both.

There are some guesses or rumours as to what it will involve, but nothing official. So here’s what we think we know.

It will involve years of disruption affecting communities including Slaithwaite & Marsden (leaked letter from Rob McIntosh of Network Rail, 10th September 2018)

It will be wonderful in a non-specific way (article in YP by the same Rob McIntosh, 14th December 2018)

It’s going to be announced in November 2018 (it wasn’t)

It’s going to be announced in December 2018 (it wasn’t)

It’s going to be announced in January 2019 (it wasn’t)

Work will start in Spring 2019 (Andrew Jones MP, Rail Minister, 10/01/2019) (it didn’t)

It probably doesn’t involve electrification between Huddersfield and Stalybridge, even though this is the hilly part of the route where electrification would bring the most benefits.

It allegedly involves four tracks from Huddersfield to Ravensthorpe (c0nfirmed on 18/08/2019).

There was apparently a consultation with passengers in July and August, carried out by Transport Focus on behalf of Network Rail. The consultation consisted of focus groups at Huddersfield, Leeds and Manchester, conveniently excluding passengers at the stations where the most disruption is likely to be matched with the least benefit. The leaked letter of 10/09/2018 is also being cited as part of the public consultation. [source: Network Rail presentation to Transport for the North Board, 12/09/2019]

Stalybridge station will be rebuilt (again) to give four through platforms. Possibly.

As to whether it will deliver full disabled access at all stations, it seems that the Department for Transport have decided that full disabled access is an optional extra which won’t be provided. We kept asking about this, and now we know why no-one was prepared to answer. More on this in a separate posting.

There might be an announcement in the Autumn. Or maybe there won’t.

Posted in Transpennine Route Upgrade | Leave a comment

ITV Tonight Programme “Trouble on the Tracks”

To be broadcast tonight, 17th January, 7.30 on ITV. Will include filming done on 15th November of the passenger experience in the morning peak from Slaithwaite & Mossley into Manchester. There may be some familiar faces.

https://www.radiotimes.com/tv-programme/e/hjqpgk/tonight/

Posted in Uncategorized | Leave a comment